Project Title: Water Supply Infrastructure Analysis
Description: Analysis of water supply infrastructure needs for dry-year water alternatives
Consultant: Brown & Caldwell
Assigned Staff: John Maguire
Contract Amount: $330,000 |
Project Title: Water Treatment Plant Pump Station Improvements
Description: Design and construction assistance services for WTP pump station improvements
Consultant: Carollo Engineers
Assigned Staff: Todd Eising
Contract Amount: $565,000 |
Project Title: Sanitary Sewer Management Plan
Description: Design services for the replacement/repair/expansion of various sewer lines
Consultant: HDR
Assigned Staff: Kyle Ericson
Contract Amount: $295,000 |
Project Title: Water Treatment Plant Expansion Project
Description: Design and construction assistance services for the WTP Expansion Project
Consultant: Malcolm Pirnie
Assigned Staff: Todd Eising
Contract Amount: $2,116,896 |
Project Title: Water Quality/Treatment Consulting Services
Description: Consulting services for water quality and treatment compliance for the WTP
Consultant: Malcolm Pirnie
Assigned Staff: Todd Eising
Contract Amount: $40,000 |
Project Title: Professional Services for Compliance with Stage 2 Disinfection Byproducts Rule
Description: The development of sampling and monitoring processes and procedures to meet new water quality regulations
Consultant: Malcolm Pirnie
Assigned Staff: Walt Sadler
Contract Amount: $143,179 |
Project Title: Water Treatment Plant Regulatory Assistance
Description: Technical assistance with regulatory compliance associated with the Water Treatment Plant
Consultant: Malcolm Pirnie
Assigned Staff: Todd Eising
Contract Amount: $288,549 |
Project Title: Community Outreach Assistance
Description: Assistance with community outreach efforts associated with various projects
Consultant: MMC Communications
Assigned Staff: Todd Eising
Contract Amount: $200,000 |
Project Title: Willow Hill Reservoir Valve Replacement
Description: Design and construction assistance services for the Willow Hill Reservoir Valve Replacement Project
Consultant: Nervick and Associates
Assigned Staff: Kyle Ericson
Contract Amount: $36,050 |
Project Title: Scada Improvements for Water Treatment Plant
Description: Installation and upgrade of communication equipment at the Water Treatment Plant in conjunction with the expansion project
Consultant: Tesco
Assigned Staff: Todd Eising
Contract Amount: $525,000 |
Project Title: Water Supply Management Services
Description: Assistance with investigating additional water supplies for dry-year conditions
Consultant: Tully & Young
Assigned Staff: Ken Payne
Contract Amount: $660,000 |
Project Title: EPA Sewer Rehabilitation Project - Phase 2
Description: Design and construction management services for replacing and rehabilitating sewer and water lines in School Street, Market Street and Duchow Street.
Consultant: Domenichelli & associates, Inc.
Assigned Staff: Marcus Yasutake
Contract Amount: $200,000 |
|
Project Title: Sewer System Master Plan Update
Description: Major update of City's sewer system master plan
Consultant: ECO:LOGIC
Assigned Staff: Kyle Ericson
Contract Amount: $150,000
|
Project Title: By-Pass Raw Water Project
Description: Engineering and feasibility analysis to evaluate the environmental and design requirements for incorporation of the raw waterline into the Folsom Dam Flood Control Project
Consultant: Camp, Dresser & McKee
Assigned Staff: Kyle Ericson
Contract Amount: $76,000 |
Project Title: Sphere of Influence Area
Description: Prepare infrastructure water and sewer studies for the sphere of influence area
Consultant: The J. Crowley Group
Assigned Staff: John Maguire
Contract Amount: $191,000 |
|
Title: By-Pass Water Supply Analysis
Description: Technical analysis of a redundant/by-pass system for the City’s water supply infrastructure from Folsom Dam
Consultant: Camp, Dresser & McKee
Assigned Staff: Kyle Ericson
Contract Amount: $68,889
|
|
Title: Sanitary Sewer System Hydraulic Capacity Study Update
Description: Annual update of the sanitary sewer system capacity study.
Consultant: ECO:Logic
Assigned Staff: Todd Eising
Contract Amount: $150,000
|
| Title: Natoma Standpipe Relocation Project
Description: Relocation of standpipe on City's main raw water supply line to eliminate conflict with construction of new bridge project.
Consultant: BCB Construction Services
Assigned Staff: Todd Eising / Marcus Yasutake
Contract Amount: $200,000
|
| Title: Oak Avenue Parkway Lift Station Modifications Project
Description: Construction management services for project involving modifications to the Oak Avenue Sewer Lift Station
Consultant: ICM Group, Inc.
Assigned Staff: Vaughn Fleischbein / Kyle Ericson
Contract Amount: $37,917
|
| Title: Orange Grove Water and Sever Rehabilitation Project
Description: Design services for the Orange Grove Water and Sewer Rehabilitation Project
Consultant: Kimley Horn and Associates
Assigned Staff: Kyle Ericson/Vaughn Fleischbein
Contract Amount: $169,209 |
| Title: Amendment No. 2 to Design Services Agreement for the Natoma Standpipe Relocation Project
Description: A contract amendment to provide construction assistance services for the Natoma Standpipe Relocation Project
Consultant: Robert W. Miles
Assigned Staff: Todd Eising/Marcus Yasutake
Contract Amount: $75,000
|
| Title: Inspection of Various Water Storage Tanks
Description: Inspection services for various water storage tanks.
Consultant: Norton Corrosion
Assigned Staff: Roy Hafar
Contract Amount: $13,620
|
Title: Clean Closure of the Corporation Yard Landfill
Description: Develop a clean closure plan and contract documents for clean closure of the Corporation Yard Landfill by a contractor, Construction Management during the closure activities and development of the final site closure report for regulatory approval
Consultant: Brown and Caldwell
Assigned Staff: Walt Sadler
Contract Amount: $615,353 |
|
Title: Water Meter Reading
Description: Meter reading services associated with the meter implementation project
Consultant: Alexander's Inc.
Assigned Staff: Todd Eising
Contract Amount: $40,000
|
| Title: Natoma Standpipe Relocation Project Amendment No. 1
Description: Additional construction management services for the Natoma Standpipe Relocation Project
Consultant: BCB Construction
Assigned Staff: Marcus Yasutake
Contract Amount: $75,000
|
| Title: Constructability Review Services
Description: Constructability review services for various upcoming capital improvement projects
Consultant: BCB Construction
Assigned Staff: Marcus Yasutake
Contract Amount: $40,000
|
| Title: Lake Forest Sanitary Sewer Lift Station Modifications
Description: Design services for modifications to the Lake Forest Sanitary Sewer Lift Station
Consultant: Black & Veatch
Assigned Staff: Todd Eising
Contract Amount: $215,00000
|
| Title: Empire Ranch Golf Course Wells Investigation - Environmental Analysis
Description: Preparation of environmental documents for development of a groundwater well system to serve the Empire Ranch Golf Course
Consultant: CH2MHill
Assigned Staff: Walt Sadler
Contract Amount: $200,000
|
| Title: Historic District Utility Rehabilitation Project, Phase II
Description: Repair/replacement of various water and sewer lines in the historic district
Consultant: Dominichelli & Associates
Assigned Staff: Marcus Yasutake
Contract Amount: $200,000
|
| Title: Historic District Utility Rehabilitation Project, Phase II - Amendment No. 1
Description: Additional design and construction management services associated with the Historic District Utility Rehabilitation Project Phase II
Consultant: Dominichelli & Associates
Assigned Staff: Marcus Yasutake
Contract Amount: $105,000
|
| Title: SOI Raw Water Pipeline Alternative Alignments Study
Description: Study of alternative alignments for proposed water pipeline to serve the SOI area
Consultant: J. Crowley Group
Assigned Staff: John Maguire
Contract Amount: $39,000
|
| Title: La Colina dal Lago Water Pump Station SCADA Improvements
Description: Installation of communication equipment at the La Colina dal Lago water pump station
Consultant: Tesco
Assigned Staff: Todd Eising
Contract Amount: $85,000
|
| Title: Sacramento County Water Agency Planning and Coordination
Description: Technical assistance with the planning and coordination of issues associated with the SOI water supply involving the Sacramento County Water Agency
Consultant: Tully & Young
Assigned Staff: Ken Payne
Contract Amount: $23,000
|
| Title: Department of Water Resources Coordination
Description: Technical assistance with the planning and coordination of issues associated with the SOI water supply involving the State Department of Water Resources
Consultant: Tully & Young
Assigned Staff: Ken Payne
Contract Amount: $15,000
|
Title: Preliminary Water Treatment Plant Presentation
Description: Preliminary facility needs analysis for future water treatment plant to serve the SOI area
Consultant: Camp, Dresser and McKee
Assigned Staff: Ken Payne
Contract Amount: $25,000 |
Title: Nimbus Tank Rehabilitation
Description: Design services for improvements to the Nimbus water storage tank
Consultant: Kimley-Horn and Associates
Assigned Staff: Marcus Yasutake
Contract Amount: $110,000 |
Title: Coordination with Sacramento County Water Agency
Description: Technical assistance and coordination with Sacramento County Water Agency relating to SOI water conveyance system
Consultant: RMC
Assigned Staff: Ken Payne
Contract Amount: $40,000 |
Title: Coordination with Sacramento County Water Agency
Description: Technical assistance and coordination with Sacramento County Water Agency relating to SOI water conveyance system
Consultant: The J. Crowley Group
Assigned Staff: John Maguire
Contract Amount: $25,000 |
|
Project Title:
Description:
Consultant:
Assigned Staff:
Contract Amount:
Project Title:
Description:
Consultant:
Assigned Staff:
Description:
Consultant:
Assigned Staff:
Contract Amount:
Project Title:
Description:
Contract Amount:
|